WORKS COMPLETED FOR LUTTEUR PROJECT
DISMANTLING
EXTERIORBoat completely stripped
All deck equipments removed (rubber fender, anchors, chain, windlass, tugging winch, towing hook, stern stanchions, mast, dorade vents, fire fighting nozzles, deck valves, crane, liferaft stands..)
2 towing arches cut off
Wheelhouse and funnel removed
Circular step on top deck dismantled
2 generator air inlets removed
All fittings on bulwarks removed and cut to 0.
2 sundeck wings cut off
Sundeck skylight cut, weighed and stored
All supports on pilothouse removed
Pilothouse stanchions removed
Engine room skylight removed
Stern soft patch removed and stored
4 rollers on bow removed and stored
Hand rail removed
Lateral airvent boxes cut at deck level
All rubber paint removed from deck
STEERING LOCKERSteering system dismantled and removed
All electricity removed
INTERIORBoat completely stripped
All electronics removed
All electricity removed
All cement removed
All plumbing and piping removed
Fittings, electric items and control boxes in wheelhouse removed and stored
All panels, ceilings and insulation removed
All portholes removed and stored
Engine room stairs removed
Port side air duct removed
ENGINE ROOMFuel tanks emptied and degassed
"Engine room stripped except for main engine: 2 generators with exhaust systems removed ; Firefighting pumps removed for maintenance; Fuel and seawater pumps removed ; Hydraulic system removed; Central heating system and fuel tanks removed ; Inverters and rectifiers removed"
All electricity including wiring, control boxes, panelsÉremoved.
All floors removed and labelled
All floors structure removed
METAL TREATMENT
In Cherbourg, before delivery, hull was completely sandblasted while out of the water, epoxy treated and repainted..
The boat was then fully sandblasted including topsides, superstructures and inside except for engine room, steering locker and chain locker. In these 3 areas, rust has been removed completely manually. And then epoxy treated.
METALWORK
All metalwork has been carried out in maritime steel plate quality under marine thickness standards.
HULLKort nozzle completely checked while out of water
Propeler completely checked
Baffles built around water outlets
Rubbing streak cut down
All dented areas straightened
Old grey water outlets plated.
BULWARKSKnees straightened or changed
Steel capping rail cut off partially (amidships to stern ) and new stainless steel capping rail base built
Knees added on stern deck
Lateral doors cut on both sides
DECKSome deck plates replaced on foredeck
Vents reinstalled and goosenecks replaced by stainless ones
Stainless steel motor pump connections built
All filling pipes replaced by stainless ones with bronze caps.
New windlass base built
Water baffles built around waterways and aft
Hand rail built around main deck
Raised deck base built over engine room
SUN DECK70% new plating
SUPERSTRUCTURESNew wheelhouse built
New funnel and air filter box built
New raised roof built
Central part of main deck roof cut out
Fwd port and stbd lateral doors to main deck cut out and replaced
Aft lateral doors plated in.
Large proportion of join between main deck and superstructures plating changed.
Large proportion of plating changed on main deck superstructure
All aft part of main deck superstructure new.
All skylight hatches removed, treated, and reinstalled with new hinge system (brass insert with stainless shaft).
Ex-captains cabin porthole plated in.
2 windows cut aft sides.
Water deflectors installed above windows and doors
CHAIN LOCKERAll rust removed and metal epoxy treated
Hatch removed, repaired, epoxy treated, painted and reinstalled
STEERING LOCKERAll rust removed and metal treated
Soft patch sandblasted, treated and painted
Entrance hatch moved to port side
New floor supports
INTERIORAll main deck bulkheads except 2 cut out
New bulkheads built as per new layout.
All interior epoxy treated and repainted
Floor structures built below
New door openings made
Ceiling beam on main deck repaired
Crew head box built
Fresh water tank and dry compartment manholes moved
Waterways built in guest cabins
ENGINE ROOMBilges dried out, treated and painted
Underfloor supports cut out
Floors sandblasted, treated and painted and some new.
Technical ducts opened in fwd and aft bulkheads and in ceiling for piping and for wiring.
New supports built for new systems
SYSTEMS
MAIN ENGINEFresh water system rinsed and winterised
Coupled air compressor removed and serviced
Exhaust insulation removed
Engine control panel removed and rebuilt
14 new manometers and thermometers
Engine control sensor checked
All main exhaust pipes fitted on silent blocks
5 metres new exhaust in funnel
Main engine and gear box checked , serviced and painted
ENGINE ROOMTurbo air duct built
New blower and extractor installed
Polluted air ventilation duct installed
New electric service pump installed (see spec sheet)
New electric fuel transfer pump installed (see spec sheet)
New electric air compressor installed (see spec sheet)
4 new electric hydraulic pumps installed (see spec sheet)
Hydraulic converted fire fighting pumps reinstalled (see spec sheet)
New Hamann Super-mini sewage plant installed (see spec sheet)
New pneumatic pump installed (see spec sheet)
New airconditioning plant installed (see spec sheet)
New watermaker installed (see spec sheet)
2 new generators installed (Kohler 50 Kva) (see spec sheet)
New fresh water pressure system installed (see spec sheet)
New boiler installed (see spec sheet)
New hot water circulation pump installed (see equipment list)
New main AC switchboard
TANKS and PIPING80% of under floor seawater piping sandblasted, controlled, repaired, epoxy treated, painted and reinstalled. 20% new for new systems.
Diesel piping: 80% as above as 20% new for new systems.
Air piping: 100% new
Hydraulic piping: 100 % new
Fresh water piping: 100% new
Black and grey water piping: 100 % new
Air ducts: 80% new
Valves: 80% removed, sandblasted, treated and fully serviced and bench tested at 12 bars. 20% new.
New non-return valves installed
New glass visual controls installed
New sea water filters installed
Stainless steel water drain pipes built and installed
Stainless steel grey and black water tanks built
Existing steering hydraulic tanks sandblasted, treated and reinstalled.
Stainless steel windlass hydraulic tank built
Stainless capstan hydraulic tank built and installed
Stainless steel expansion built and installed tank for main engine
Vent pipes changed to new interior flexible piping
Day tank stainless vent fitted on main deck
New Kuebler magnetic level gauge installed for day tank
New Kuebler level gauges installed for fresh water tanks
14 stainless steel strum boxes installed on all suction pipes
All manometers have been fully checked and serviced.
MISCELLANEOUSHydraulic steering system removed and completely renewed.
Kort nozzle and propeller completely checked
Windlass converted to hydraulic system reinstalled
STUDIES AND CLASSIFICATION
Complete design study of 2 layout versions (Butch Design & Jacques Louvet))
Complete electrical circuit and alarms study (Eric Perryman)
Full hull thickness measurements (Foure Lagadec)
Historic file and original plans (French Navy & CMN archives compiled by Jacques Louvet)
Bureau Veritas classification underway
Full quotation for project completion
Procedure book under completion including all technical drawings (Olivier Mesle)